18. The standard time required per unit of a
product is 20 minutes. In a day of 8 working
hours, a worker gives an output of 30 units
If he gets a time rate of 20 per hour, his total
earnings under Halsey Plan was
O 160
O 180
Answers
Answered by
0
Answer:
cl and the rest 3
Explanation:
Hey I was wondering why I didn't get the chance of winning a new delhi for a long way
Answered by
0
Explanation:
Given 18. The standard time required per unit of a product is 20 minutes. In a day of 8 working hours, a worker gives an output of 30 units. If he gets a time rate of 20 per hour, his total earnings under Halsey Plan was
O 160
O 180
- So under Halsey scheme we have
- Earnings = hours worked x rate per hour + (50% x time saved x rate per hour) ------------------ 1
- Time allowed per unit of a product is 20 minutes
- So for 30 units it will be 30 x 20 = 600 minutes
- = 600 / 60
- = 10 hours.
- So for the worker in a day time taken is 8 hours.
- Now the worker will have a time of 10 – 8 = 2 hours.
- So the worker for 8 hours gets 20 x 8 = Rs 160
- Now substituting this in equation 1 we get
- Earnings = 8 x 20 + (50/100 x 2 x 20)
- = 160 + (1/2 x 2 x 20)
- = 160 + 20
- = Rs 180
- Therefore the total earnings will be Rs 180