Math, asked by VishalVairalPatil, 11 months ago

18 Workers can make 45 tables in 21 Days, then how many Days would it take for 14 Workers
to make 25 tables?​

Answers

Answered by janvitha
1

Answer:

15DAYS

Step-by-step explanation:

18*21/45=14*D/25

D=18*21*25/45*14

=15

Similar questions