18 Workers can make 45 tables in 21 Days, then how many Days would it take for 14 Workers
to make 25 tables?
Answers
Answered by
1
Answer:
15DAYS
Step-by-step explanation:
18*21/45=14*D/25
D=18*21*25/45*14
=15