19._ is the process of testing the
feasibility of master
production
schedules in terms of capacity.
a. Rough-cut capacity planninger
b. Manpower planning
c. Financial planning
d. Machine planning
Answers
Answered by
0
Answer:
rough cut capacity planning
Explanation:
Resource Requirement Planning Resource requirement planning (rough-cut capacity planning) is the process of testing the feasibility of master production schedule in terms of capacity.