19 men working 7 1/2 hours a day can finish a job in 21 days. How many hours a day must 45 men work to complete it in 7 days?
PLZ do it ASAP
PLZ
Answers
Answer:
19 men take 21 days working 15/2 hours per day.
Hours per day 45 men will take to complete in 7 days will be:
if 19 men = 15/2 hours
then 45 men = 19/45 hours ( this because the 45 men will take less hours per day, hence you use the lesser fraction of the two values)
if 21 days = 15/2 hours per day
then 7 days= 21/7 (this because the hours required will be more, hence you use the larger fraction of the two values)
therefore the calculation is = 15/2 x 19/45 x 21/7
= (15x19x21)/(2x45x7)
= 19/2
= 9.5 hours per day
Answer:
I was also having a doubt in this question but the above answer has made me clear and it is also the correct answer (I have already checked).So,I want to reward it with you like as well as rate it as EXCELLENT.