195 men working 10 hours a day can finish a job in 20 days. How many
men are employed to finish the job in 15 days if they work 13 hours a day?
Answers
Answered by
4
Answer:
Solution :- The work requires 195*10*20 = 39000 men-hour-days. = 200 men.
Step-by-step explanation:
Hope this answer helps you