Math, asked by raghavpateriya792, 3 months ago

2. 120 men working 9 hours a day can construct a road
in 40 days. How long would it take to construct the
same road if 150 men work 6 hours a day on it?

Answers

Answered by Anonymous
0

Step-by-step explanation:

120 men working 9 hours a day can construct a road

in 40 days. How long would it take to construct the

same road if 150 men work 6 hours a day on it?

Answered by Akshara8088
2

Step-by-step explanation:

48 days is your answer

.........

thanks

Similar questions