2. A can do a piece of work in 12 days, B can do the
same work in 15 days and A, B and C together
can finish the work in 5 days. In how many days
will C alone complete the work?
Answers
Answered by
1
Answer:
18 days
.................. .
Answered by
2
might be 18 days is your answer
hope this helps you
thanks