Math, asked by retik22, 2 months ago


2. A can do a piece of work in 40 days; B can do the same in 30 days. A started alone but left the work after 10 days, then B
worked at it for 10 days. C finished the remaining work in 10 days. Calone can do the whole work in?
A. 24 days B. 30 days C. 44 days D. 17 1/2 days
3. A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can
do it in:
A.20 days B.22 days C.25 days D.30 days E. None of these
4. If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time
taken by 15 men and 20 boys in doing the same type of work will be:
1.7 days
left the job. In how many
Us

Answers

Answered by mitalichak2012
0

2a.24days

3b.22whole1\2

4.c. 4days

Step-by-step explanation:

2.Let the total work be x units.

A can do the work in 40 days. 1 day work of A = x/40

B can do the work in 30 days. 1 day work of B = x/30 =

For the first 10 days A does the work alone.

10 ays work of A = 10 x x/40 = x/4

For the next 10 days B does the work alone.

10 days work of B = x/3C does the remaining work left in the last 10 days .

x = 10 days work of C + x/3 + x/4

=> 10 days work of C = 5 x/12

C can do 5x/12 units of work in 10 days. C can do x units of work in = (x x 10)/(5x/ 12)

= 24 days

3.Ratio of times taken by A and B =1:3

The time difference is (3−1)2 days while B takes 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes (

2

3

×60)=90 days.

So, A takes 30 days to do the work.

A's 1 day's work =

30

1

B's 1 day's work =

90

1

(A+B)'s 1 day's work =(

30

1

+

90

1

)=

90

4

=

45

2

∴ A and B can do the work in

2

45

=22

2

1

days.

4.Given that

6 men and 8 boys can do a piece of work in 10 days

26 men and 48 boys can do the same in 2 days

As the work done is equal,

10(6M + 8B) = 2(26M + 48B)

60M + 80B = 52M + 96B

=> M = 2B

=> B = M/2 ……(1)

Now Put (1) in 15M + 20B

=> 15M + 10M = 25M

Now, 6M + 8B in 10 days

=> (6M + 4M) 10 = 100M

Then D(25M) = 100M

=> D = 4 days.

Similar questions