2 Gents and 5 Ladies complete a work in 4 dyas. 4 Gents and 4 Ladies takes
days to complete the same work. Then how many days need to complete the
same work for a single Gents or Ladies?
Answers
2 Gents and 5 Ladies complete a work in 4 dyas. 4 Gents and 4 Ladies takes *3 days to complete the same work.
12 days are needed to complete the same work for a single Gents and Ladies.
Let one gent take x days to complete the work.
So, work done by him in one day = 1/x
Let one lady take y days to complete the work.
So, work done by him in one day = 1/y.
Given, 2 gents and 5 ladies complete a work in 4 days.
Thus, 2/x + 5/y = 1/4
⇒ 2y + 5x = xy/4 [Multiplying both sides by xy]
⇒ 8y + 20x = xy [Multiplying by 4 on both sides]
⇒ 96y + 240x = 12xy [Multiplying by 12 on both sides] ...(1)
Again 4 gents and 4 ladies takes 3 days to complete the work.
Thus, 4/x + 4/y = 1/3
⇒ 4y + 4x = xy/3 [Multiplying by xy on both sides]
⇒ 12y + 12x = xy [Multiplying by 3 on both sides]
⇒ 96y + 96x = 8xy [Multiplying by 8 on both sides] ...(2)
Subtracting (2) from (1),
240x - 96x = 12xy - 8xy
⇒ 144x = 4xy
⇒ y = 144/4 = 36
As 8y + 20x = xy
So, 8(36) + 20x = x(36)
⇒ 20x + 288 = 36x
⇒ 16x = 288
⇒ x = 288/16 = 18
Let one gent and one lady take 'd' days.
So, 1/x + 1/y = 1/d
⇒ 1/18 + 1/36 = 1/d
⇒ 3/36 = 1/d
⇒ 1/d = 1/12
⇒ d = 12
12 days is the answer.