2. If 18 men can do a work in 20
days, then 24 men can do this
work in (days)​

Answers

Answered by ajay8949
3

Answer:

18 men's do a work in = 20 days

1 men can do a work in = 20 /18 days

24 men can do a work in = 20/18×24

= 360/24

= 15 days

please mark as brainliest

Answered by dhanasekartool
0

Answer:

15 days.

Step-by-step explanation:

18 * 20 = 24 * x

360 = 24 * x

x = 360 / 24

x = 15 days