2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can dot he same work in 8 days . in how many days can 2 men and 1 boy do the work

Answers

Answered by MinulataNayak
2
2 Men + 3÷100=1÷10
2 Men = 1÷10-3÷100
2 Men = 7÷100
2 Men + 1÷Boys = 7/100+1/100= 8/100
So, time taken 100/8 = 12.5
Your answer is 12.5