2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 15 days. In how many days can 1 man and 1 boy do the work?
Answers
Answered by
0
Here I will use the concept of
Man*Days
(2m+3b) 10 = (3m+2b) 8
20m+30b = 24m+16b
14b = 4m
7b = 2m
So 2m = 7b
Now
(2m+3b) 10 = (2m+1b) x
(7b+3b) 10 = (7b+1b) x
10*10 = 8*x
X = 100/8
X = 12.5 days