2 men and 5 boys can finish a piece of work in 4 days,while 3 men and 6 boys can finish it in 3 days. find the time taken by one man alone to finish the work and that taken by one boy alone to finish the work.
Answers
Answered by
4
man 48 days , boys 24 days will be the answer
Attachments:
Similar questions