2 men and 7 chlindren complete a certain peiece of wokk in 4 days and 4 men and 4 children complete the same in 3 days find number of days required to complete the same work by one men and 1 child
Answers
Answered by
0
2/x+7/y=1/4
4/x+4/y=1/3
1/x=a 1/y=b
2a+7b=1/4
4a+4b+1/3
if u solve tis eq u will get the ans dude
4/x+4/y=1/3
1/x=a 1/y=b
2a+7b=1/4
4a+4b+1/3
if u solve tis eq u will get the ans dude
priya23774828:
and 1/y=b so y=60