2 men can do a peice of work in 10 days. How many men are needed to complete the work in 5 days
Answers
Answered by
2
Answer:
2 men do a work =10days
1 men do a work =10*2
=20
men needed to do the same work in 5days
= 20/5
=4 men
Step-by-step explanation:
mark as brainlist
Answered by
8
Answer:
answer 4 men
Step-by-step explanation:
please mark me as brainiest