Math, asked by Kushaaaaaan, 5 months ago

2 men can do a work in 4 days and 6 days respectively. if they work together, in how. many days will they finish the work​

Answers

Answered by Cynefin
42

Solution:

The number of days taken by two men is given in the question and we have to find the total number of days they will take to complete work together.

GiveN:

  • Time taken by A = 4 days
  • Time taken by B = 6 days

To find the time taken when they work together...?

So, let's start solving....

  • 1 day's work of A = 1/4
  • 1 day's work of B = 1/6

If they work together, there one day work would be:

➝ 1/4 + 1/6

➝ 4 + 6/24

➝ 10/24

➝ 5/12

So, In one day A and B can complete 5/12 of the work, So total number of days taken by them to complete together:

\large{ \boxed{ \red{ \bf{ \frac{12}{5} = 2.4 \: days}}}}

And we are done !

Similar questions