English, asked by AvailableLiver10, 6 months ago

2 men or 3 boys can finish a work in 48 days. In
how many days will 4 men and 6 boys finish the work?​

Answers

Answered by amrita230905
1

Answer:

Explanation:

Let work of each man be x

Work of each boy be y

(2*x)+(3*y)=(1\48)—equation 1

(4*x)+(6*y)=?

Multiplying equation1 with 2 on bothsides

?=(2*(1\48))=(1\24)

Hence no of days will be 24

Answered by sasmitsrivastava0201
6

Answer:

12 days     easiest explanation

Explanation:

2 men= 3 boys

6 boys=4 men

4 men+6 boys=4 men+4 men=8 men

2 men=48 days

1 man=96 days

8 men=12 days

Similar questions