2 men or 4 women can finish a work in 10 days how long will 6 men and 8 women take to finish the same work
Answers
say , work done by 1 woman per day = x
and " by 1 man per day = y
In question
2× 10 ×y = 4× 10×x
20y= 40x
Total work done can be 20y or 40x
y = 2x
since I am substituting x with y
let d be th no of days to finish work
Then
(6×y + 8×x ) × d= 40x
(6 × 2x + 8× x) × d = 40x
20x ×d =40x
d = 40/20 = 2
:. Total no of days taken to complete is 2
MARK AS BRAINLIEST PLEASE
Answer:
QUESTION:-
2 men or 4 women can finish a work in 10 days how long will 6 men and 8 women take to finish the same work.
SOLUTION:-
2 men or 4 women can finish a work in 10 days = 10 days
:. Time 6 men and 8 women take to finish the same work = 1 man can finish a work in 20 days & a man can finish his 1 in 1 day.
20
4 women can finish a work in 10 days. So, 1 women can finish the same work 1 of work in 1 day. 40
6 man can finish 1*6 = 6 of work in 1 day.
20 20
8 women can finish 1*8 = 8 = 1 of work in 1 day. 20 40 5
6 men and women together can finish= 6 + 1 20
5
6 men and women together can finish= (6 + 4)
20
6 men and women together can finish= 10
20
6 men and women together can finish= 1 in 1 day 2
6 men and women together can finish entire work in 2 days.