A job takes 12 days to get completed by 2 men.
1 task = (12 days) x (2 men) = 24 man-days.
Therefore, the job requires 24 man-days to get completed. In other words, it would take 24 days for a man to complete the job.
Now, if you have 20 men, how many days would take to complete the same job?
1 task = (X days) x (20 men) = 24 man-days
X = (24 man-days) / (20 men)
X = 1.2 days