2 people can plough a field in 6 hours. A how long would it take one person to plough the Field? B how long would it take 3 people to plough the field?
Answers
Answered by
7
Answer:
- 2 people can plough a field in 6 hours.
- How long would it take 1 person to plough the field?
- How long it take 3 people to plough the field.
Solution :-
1) → Time taken by two people to plough the field = 6 hours.
→ Time taken by 1 person to plough the field :-
→ 6 × 2 = 12 hours.
2)→ Time taken by 3 people to plough the field.
→ (6÷3)×2
→ 2 × 2 = 4 hours