2 people plough a field in 6 hours
how long would it take 1 person to plough the field?
how long would it 3 people to plough the field?
Answers
Answered by
3
Answer:
12 hours and 4 hours
Step-by-step explanation:
2 people plough a field in 6 hours
1 man can plough the field in 6×2 hours = 12hours
3 people can plough the field in 12÷3 hours = 4hr