Math, asked by fayazahmad6007, 11 months ago

2 persons can complete a piece of work in 90 days . How many more persons are needed to complete thrice the work in 12 days

Answers

Answered by Tasmai
0

Answer:

15 Person

Step-by-step explanation:

2*90/12 =15 Please follow me