2) Revised estimate is prepared when __________
a) There is a dispute between owner & contractor
b) When the expenditure of the project is increased by 2%
c) When there is change in design, drawing and material deviation
d) All of the above
Answers
Answered by
0
Answer:
Revised cost estimate is a detailed estimate and it is prepared when the original sanctioned estimate value is exceeded by 5% or more.