Math, asked by lakshmisahoosahoo, 11 months ago

2 women and 5 men can together finish an embroidery work in 4 days while 3 women
and 6 men can finish it in 3 days. Find the time taken by 1 woman alone and I man
alone to finish the work.​

Answers

Answered by vedavivek
14

Answer:

let 1 women =x

let 1 man=y

from given info

2x+5y=4

3x+6y=3

x+2y=1

sub (1)and (2)

2x+5y=4

x+2y=1

x+3y=3

x=3-3y....(3)

sub (3) in (2)

x+2y=1

3-3y+2y=1

3-y=1

y=2

x=3-3(2)

x=3-6

x=3(as no of people can't be negative)

x+y=2+3

=5

so,for one man and one women it would take 5days

Answered by SoumithG26
0

Hi there. Your answer is in the attachment above.

A woman alone can finish the embroidery work in 36 days.

A man alone can finish the embroidery work in 18 days.

Hope you're doing great.

STAY SAFE :-)