Math, asked by srijanshouryaman99, 7 months ago

2 women and 5 men can together finish an embroidery work in 4 days, while 3 women and 6 men can finish it in 3 days . Find the time taken by 1 women alone to finish the work, also that taken by 1 man alone.

Answers

Answered by Anonymous
83

Let us assume that, the time taken by woman to complete the work be x days and by man be y days.

2 women and 5 men can together finish an embroidery work in 4 days.

According to question,

⇒ 2/x + 5/y = 1/4

⇒ (2y + 5x)/xy = 1/4

⇒ 4(2y + 5x) = xy

⇒ 8y + 20x = xy...........(1)

On the other hand, 3 women and 6 men can finish it in 3 days.

According to question,

⇒ 3/x + 6/y = 1/3

⇒ (3y + 6x)/xy = 1/3

⇒ 3(3y + 6x) = xy

⇒ 9y + 18x = xy............(2)

On multiplying (eq 1) with 9 and (eq 2) with 8 we get,

⇒ 72y = 9xy - 180x...........(3)

⇒ 72y = 8xy - 144x...........(4)

On comparing we get,

⇒ 9xy - 180x = 8xy - 144x

⇒ 9xy - 8xy = - 144x + 180x

⇒ xy = 36x

⇒ y = 36 days

Substitute value of y in (eq 1)

⇒ 8(36) + 20x = 36x

⇒ 288 = 36x - 20x

⇒ 288 = 16x

⇒ x = 18 days

Therefore,

Woman alone can finish the work in 18 days and man alone in 36 days.


Nereida: Great Manu :D
Anonymous: Thanku :P
Answered by RvChaudharY50
56

||✪✪ GIVEN ✪✪||

  • 2W + 5M can Together Finish a work in = 4 days.
  • 3W + 6M can Together Finish a work in = 3 days.

✯✯ To Find ✯✯

  • Time Taken by 1 woman Alone ?
  • Time Taken by 1 man Alone ?

|| ✰✰ ANSWER ✰✰ ||

Given That, 2 women and 5 men can together finish an embroidery work in 4 days .

So,

➻ Total work = 4(2W + 5M) .

Similarly, 3W + 6M can Together Finish a work in = 3 days.

So,

Total work = 3(3W + 6M)

___________________

Now, Since Work is Same in Both Case ,

So,

⟼ 4(2W + 5M) = 3(3W + 6M)

⟼ 8W + 20M = 9W + 18M

⟼ 20M - 18M = 9W - 8W

⟼ 2M = 1W

⟼ (M/W) = (1/2).

______________

So, we Can say That :-

Efficiency of 1 Man = 1 unit /day.

Efficiency of 1 woman = 2 unit/day.

______________

Total work :-

4(2w + 5M)

4(2*2 + 5*1)

4(4 + 5)

4 * 9

36 units.

______________

Now,

☛ Time Taken by 1 woman Alone to Complete Total work = (36/2) = 18 days.

☛ Time Taken by 1 man Alone to Complete Total work = (36/1) = 36 days.

•°• 1 woman alone can complete the work in 18 days and 1 man alone can complete the work in 36 days.


Nereida: Awesome !
Similar questions