2 women and 5 men can together finish an embroidery work in 4 days, while 3 women and 6 men can finish it in 3 days. find the time taken by 1 women alone to finish the work and also time taken by 1 man alone.
Answers
Answered by
5
Step-by-step explanation:
This is the answer
Hope u like it
Attachments:

Answered by
2
Answer:
1 Women= 18days.
1 Men = 36days.
Attachments: