Math, asked by Yashchaudhari0511, 11 months ago

2 women and 5 men can together finish an embroidery work in 4 days . While 3 women and 6 men can finish it in 3 days . Find the time taken by 1 women alone to finish the work. And also that taken by 1 man alone.

Answers

Answered by anithaajith1981
18

Hey mate,

Hope it helps...

Plz mark me brainliest......

Attachments:
Answered by ZaraAntisera
2

Answer:

Number of days taken by a woman = 18

Number of days taken by a man = 36

Step-by-step explanation:

Let the number of days taken by a woman and a man be x and y.

= 4(2/x + 5/y) = 1

=  2/x + 5/y = 1/4

=  3(3/x + 6/y) = 1

=  3/x + 6/y = 1/3

Putting 1/x = p and 1/y = q in these equations,

we get ⇒ 2p + 5q = 1/4

By cross multiplication, we get

= p/-20 - (-18) = q/-9 - (-18)

= 1/144b- 180 = p/-2

= q/-1 = 1/-36 = p/-2

= - 1/36 and q/-1 = 1/-36

p = 1/18 and q = 1/36

p = 1/x = 1/18 and q = 1/y = 1/36

x = 18 and y = 36

Number of days taken by a woman = 18

Number of days taken by a man = 36