2 women, five men
can together finish.
an embroydery work!
in 4days while 3 women
6 men can finish it
in 3 days find
time taken by one
Alone women alone and
one men alone to finish
the work
Answers
Question -
2 women, 5 men can together finish an embroydery work in 4 days while 3 women 6 men can finish it in 3 days. Find the time taken by one women alone and one man alone to finish the work.
Step-by-step solution -
Let time taken by one woman to complete the work be x and time taken by one man to complete the work by y.
Given conditions are :
...(1)
...(2)
2 women, 5 men can together finish a piece of work in 4 days.
...(3)
3 women 6 men complete a piece of work in 3 days.
...(4)
Now,
On multiplying equation (3) with 9 and equation (4) with 8 we get,
...(5)
...(6)
On comparing equation (5) & (6) we get,
Substitute value of x in equation (4)
•°• Time taken by one woman to complete the work is 18 days and on man is 36 days.
Solution
Case I
Let the time taken by 1 woman to finish the embroidary work be x days
So, Work done by 1 women in 1 day =
Work done by 2 women in 1 day =
Let the time taken by 1 man to finish the embroidary work be y days
So, Work done by 1 man in 1 day =
Work done by 5 man in 1 day =
Total time taken to finish the work by 2 women and 5 men to finish the work = 4 days
Work done by 2 women and 5 men in 1 days =
Case II
Work done by 3 women in 1 day =
Work done by 6 men in 1 day =
Total time taken to finish the work by 3 women and 6 men to finish the work = 3 days
Work done by 3 women and 6 men in 1 days =
Now, substituting a = 1/x and b = 1/y in (1) & (2)
→ 8a + 20b = 1 ----- (3)
→ 9a + 18b = 1 ------ (4)
LCM of 8 and 9 is 72. Multiply (3) with 9 and (4) with 8. Equations will be :
i.e ( 8a + 20b = 1 ) * 9
→ 72a + 180b = 9 ---- (5)
i.e ( 9a + 18b = 1 ) * 8
→ 72a + 144b = 8 --- (6)
Subtracting (6) from (5)
→ 72a + 180b - ( 72a + 144b ) = 9 - 8
→ 72a + 180b - 72a - 144b = 1
→ 36b = 1
→ b = 1/36
But b = 1/y
→ 1/36 = 1/y
→ y = 36
Substituting b = 1/36 in (4)
But a = 1/x
→ 1/18 = 1/x
→ x = 18