Math, asked by rishusingh53, 1 month ago

20. 16 men are able to complete a piece
of work in 12 day's working 14 hours
a day. How long will 28 men, working
12 hours a day, take to complete the
work?
(1) 10 days
(3) 8 days
(2) 7 days
(4) 6 days
(SSC Constable (GD)
Exam. 2015 (Ist Sitting)​

Answers

Answered by atharv191019
0

Answer:

8 days

Step-by-step explanation:

16 men are able to complete a piece of work in 12 days working 14 hours a day.

...

Correct Option: C.

⇒ x = 16 × 14 × 12 = 8 days

28 × 12