20. If 18 men can do a work in 15 days. In how many days will 60 men complete double the work?
(a) 18 days (b) 12 days (c) 9 days (d) 10 days
Answers
Answered by
34
Step-by-step explanation:
If 18 men can do a work in 15 days. In how many days will 60 men complete double the work?
(a) 18 days (b) 12 days (c) 9 days (d) 10 days
9days
if 18 man can do in 15 days
then one man can do in 15 × 18 days
then 60 men can complete in 15 x 18/60 = 4.5 days
so 60 men can finish twice the work in 4.5×2= 9days