Math, asked by XxTankyxX, 3 months ago

20 laborers take 15 days to complete any work. How many laborers must be added to complete the same work in 12 days?

Answers

Answered by roshnekothary
0

Answer:

25 labourers

Step-by-step explanation:

as 20×12/15=25(ans)

Answered by RubiSingh315
7

Answer:

Ans - 5 Laborers

Hope! my answer is correct

Attachments:
Similar questions