20 labourers complete the construction of a building in 24 days. In how many days would 16 labourers complete the construction ?
IN RATIO FORM. QUESTION FROM RATIO AND PROPORTION CHAPTER
Answers
Answered by
0
Answer:
19.2 days
Step-by-step explanation:
let x be the missing days
20 : 24 = 16 : x
multiply 24 by 26 and 20 by x
24 (16) = 20(x)
384 = 20x
divide both sides by 20
384/20 = 20x/20
19.2 = x
Answered by
0
Answer:
The above condition is in inverse variation
we know, x=k/y
1st case
x=24,y=20
24=k/20
k=25×20
k=480
2nd case
y=16,then x=?
we know,
x=k/y
x=480/16
×=30
Therefore, 16 labourers will take 30 days.