Math, asked by manjeetdhaka1992, 8 months ago

20 men can complete the work in 40 days. When should 4 men leave so that the work may be
finished in 45 days
(
Aday's
(B..8 days
(C) 6 days
(D) 10 days​

Answers

Answered by agnivaray
0

Answer:

The answer is 15 days.

Step-by-step explanation:

20 men can complete a work in 40 days.

Total men days work

= 20 men × 40 days.

= 800 men days

When should 4 men leave so that the work may be finished in 45 days?

Now 4 men leave thus men available = 20 men - 4 men = 16 men

16 men will work for 45 days

The work completed by 16 men

= 16 × 45

= 720 men-days of work.

Remaining work = 800 men days - 720 men days = 60 men-days

These 60 men days work will be done by 4 men.

No of days required to finish the work

= 60 men - days / 4 men

= 15 days

Answered by yaashvi1427
0

20 men can complete a work in 40 days.

Total men days work

= 20 men × 40 days.

= 800 men days

When should 4 men leave so that the work may be finished in 48 days?

Now 4 men leave thus men available = 20 men - 4 men = 16 men

16 men will work for 48 days

The work completed by 16 men

= 16 × 48

= 768 men-days of work.

Remaining work = 800 men days - 768 men days = 32 men-days

This 32 men days work will be done by 4 men.

No of days required to finish the work

= 32 men - days / 4 men

= 8 days