20 men can do a piece of work in 15 days. if 10 men leave the group after 10 days how many more days will the rest of the workers take

Answers

Answered by TheBrainliestUser
139

Answer:

  • The rest of the workers will take 10 more days to complete the work.

Step-by-step explanation:

Given that:

  • 20 men can do a piece of work in 15 days.
  • 10 men leave the group after 10 days.

To Find:

  • How many more days will the rest of the workers take to complete the work.

First finding the work done by 20 workers in 10 days:

∵ 20 men can do a piece of work in 15 days.

∴ 20 men's one day work = 1/15

∴ 20 men's 10 days work = 10/15

Finding the remaining work:

  • Remaining work = 1 - 10/15
  • Remaining work = (15 - 10)/15
  • Remaining work = 5/15 = 1/3

Finding the remaining workers:

  • Remaining workers = 20 - 10
  • Remaining workers = 10

Finding the time taken by 10 man to complete the work:

∵ 20 men can do a piece of work in 15 days.

∴ 1 man can do a piece of work in (15 × 20) days.

∴ 10 men can do a piece of work in (300/10) days.

∴ 10 men can do a piece of work in 30 days.

Finding the time taken by rest workers to complete the remaining work:

∵ 10 men can do a piece of work in 30 days.

∴ 10 men can complete 1/3rd work in (30 × 1/3) days.

∴ 10 men can complete 1/3rd work in 10 days.

Answered by Anonymous
99

Given :-

If 20 men can do a piece of work in 15 days. if 10 men leave the group after 10 days

To find :-

Total ore days will the rest of the workers take

Solution :-

Work done by 20 people in 15 days = 20/15

Work done by 1 people in 15 days = 1/15

Work done by 10 people in 15 days = 10/15

Remaining work = (1)(15) - 10/15

=> 15 - 10/15

=> 5/15

=> 1/3

Remaining workers = 20 - 10 = 10 workers

Now

Work done by 10 men = 15 × 20/10

=> 300/10

=> 30 days

Now

Rest taken = 30 ×  Remaining work

Rest taken = 30 × 1/3

Rest taken = 10 days

\\