20 men can do a piece of work in 15 days. if 10 men leave the group after 10 days how many more days will the rest of the workers take
Answers
Answer:
- The rest of the workers will take 10 more days to complete the work.
Step-by-step explanation:
Given that:
- 20 men can do a piece of work in 15 days.
- 10 men leave the group after 10 days.
To Find:
- How many more days will the rest of the workers take to complete the work.
First finding the work done by 20 workers in 10 days:
∵ 20 men can do a piece of work in 15 days.
∴ 20 men's one day work = 1/15
∴ 20 men's 10 days work = 10/15
Finding the remaining work:
- Remaining work = 1 - 10/15
- Remaining work = (15 - 10)/15
- Remaining work = 5/15 = 1/3
Finding the remaining workers:
- Remaining workers = 20 - 10
- Remaining workers = 10
Finding the time taken by 10 man to complete the work:
∵ 20 men can do a piece of work in 15 days.
∴ 1 man can do a piece of work in (15 × 20) days.
∴ 10 men can do a piece of work in (300/10) days.
∴ 10 men can do a piece of work in 30 days.
Finding the time taken by rest workers to complete the remaining work:
∵ 10 men can do a piece of work in 30 days.
∴ 10 men can complete 1/3rd work in (30 × 1/3) days.
∴ 10 men can complete 1/3rd work in 10 days.
Given :-
If 20 men can do a piece of work in 15 days. if 10 men leave the group after 10 days
To find :-
Total ore days will the rest of the workers take
Solution :-
Work done by 20 people in 15 days = 20/15
Work done by 1 people in 15 days = 1/15
Work done by 10 people in 15 days = 10/15
Remaining work = (1)(15) - 10/15
=> 15 - 10/15
=> 5/15
=> 1/3
Remaining workers = 20 - 10 = 10 workers
Now
Work done by 10 men = 15 × 20/10
=> 300/10
=> 30 days
Now
Rest taken = 30 × Remaining work
Rest taken = 30 × 1/3
Rest taken = 10 days