20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men joined. In how many days is the remaining work completed?
Answers
Answered by
2
20 men=18 days
=work done by 20 men working
together =1 work
=work done by them in 3 days working
15 work to be done
efficiency of 20 men = 1
therefore 12 days more will be taken to complete the work