20 men can do a piece of work in 30 days after for how many days 5men leave the work so that the entire work will completed in 35 days
Answers
Answered by
1
Answer:
three weeks and twenty five men
Answered by
2
First of all we convert it in unit like this
20 workers × 30 days = 600 units work
After leave the 5 workers , we have 35 days for complete the work.
In 35 days only 15 workers will do the work.
So the work completed in 35 days by 15 workers = 35 ×15 =525 units
Remaining unit = 600 -525 =75 units
This units would done by 5 workers in ( 75/5) = 15 days .
So after 15 days 5 workers should leave the job.