20 men can do a piece of work in 30 days. After working for how
many days should 5 men leave the work so that the whole work will
be completed in 35 days.
Answers
Answered by
1
Answer:
20 workers will first do work for 15 days, then 5 workers will leave and then remaining 15 workers will complete the work in 20 days. Total time taken will be 35 days. Hence, the answer to the question is 15 days