20 men can do a work in 20 days. How many more men are needed to complete the work in 5 days.
Answers
Answered by
0
Answer:
5 more are needed
Step-by-step explanation:
If 20 men can do the work in 20.
5 men can do the work in 5 days
Answered by
0
Answer:
x=5, 5 men need
Step-by-step explanation:
Men= 20,x
Days=20,5
20/20=x/5. (cross multiply )
20*5=20*x
100=20x
x=100/20
x=5