Math, asked by 20101007801daisy, 6 months ago

20 men can do a work in 20 days. How many more men are needed to complete the
work in 5 days?​

Answers

Answered by 2797neil
3

Answer:

Total Men = 80

Extra Men Needed = 80 - 20 = 60

60 more men are needed to complete the work in 5 days.

Step-by-step explanation:

Total Work = Number of Men × Number of Days

⇒ 20 × 20

⇒ 400

To complete the work in 5 days

Number of Men Needed = Total Work / Number of Days

⇒ 400/5

⇒ 80 Men

Answered by bharatibehera01
1

Step-by-step explanation:

Men can do work in 20 days = 20 men

Time taken =20 days

= Distance = speed×time

=20×20

=400

Men needed to complete the work in 5 days

=400/5

=80 men

= Extra men needed = 80-20 = 60 men

HOPE IT IS HELPFULL TO YOU