Math, asked by ksudheer203, 11 months ago

20 men can finish a piece of work in 30 days. After how many days should 5 men leave the work so that
is finished in 35 days?

Answers

Answered by samitray
2

Answer:

15days

Step-by-step explanation:

20 men X 30 days = 600 mandays

x number of day worked by 20 men

20x + 15(35-x) = 600

5x = 600-525

x =15