20 men can finish a piece of work in 30 days. After how many days should 5 men leave the work so that
is finished in 35 days?
Answers
Answered by
2
Answer:
15days
Step-by-step explanation:
20 men X 30 days = 600 mandays
x number of day worked by 20 men
20x + 15(35-x) = 600
5x = 600-525
x =15