20 men can finish a work in 25 days then 5 men will finish the same work in how many days
Answers
Answered by
0
Answer:
16 more days
Step-by-step explanation:
The work requires 20 men x 25 days = 500 man-days.
In the first 5 days, the work done was 20x5 = 100 man-days worth and what remained was 400 man-days worth.
So if 5 more men were added from 6th day onwards, the remaining work will be done in 400 man-days/(20+5) men = 16 more days.
Answered by
0
Answer:
100
Step-by-step explanation:
20 men can finish a work in 25 days
1 men can finish a work in =20×25
5men can finish a work in=20×25/5
= 100
Hope it is helpful for you
pls give me Brainliest