20 men can finish a work in 30 days. on completion of 10 days, 10 men leave work. remaining men work for next 10 days. at the end of 20 days it is decided to complete the work in remaining 10 days. how many extra men are required

Answers

Answered by Sonupal
6
20*30=600 work days
20*10-200 work days completed
600-200=400 more work days
10*10=100 work days completed in 10 more days
400-100=300 more work days to complete the job
300 worker days/10 days=30 workers needed to finish the job in 10 more days
Add 20 more workers.



Answered by shravan687
3

Answer: 20 men

Step-by-step explanation

Total work unit=20*30=600

Here 20 men work for 10 days

Then,

Remaining men after 10 days=20-10=10 men

Let, men=M

We know,

Total work=men*days

ATQ,

20men*10 days+10men*10 days+10days*M=600

=200+100+10M=600

=300+10M=600

=10M=300

=M=300/10=30 men

Additional men required=30-10=20 men