20 men completed a work in 25 days. how many can complete the same work in 10 days?​

Answers

Answered by ranjanayush4001
0

Answer:

8 mens are required

Step-by-step explanation:

25 days are required for 20 men

1 day is required for 20/25 men

10 days are required for 20/25 × 10 i.e.,8 men

Answered by sikhagogoi86
1

Answer:

No. of men needed by to complete a work in 25days = 20

No. of men needed to complete the work in 1 day =20/25

Therefore, no. of men needed to complete the work = (20/25) × 10

= (4/5) × 10

=8 men