20 men decided to complete the repairing work of a house in 30 days.but after 6 days 8 men fell sick.let's find, how long they will take to complete the work
please write the answer immediatly
Answers
Answered by
11
Step-by-step explanation:
20*30 = 600 men-days.
2. 20*6 = 120 men-days
3. 600 - 120 = 480 men-days.
4. 20 - 8 = 12 men remained.
5. 480%2F12 = 40 days.
Answer. It will take 6 + 40 = 46 days to complete the job, counting from the very fist day
Answered by
2
Answer:
46days
Step-by-step explanation:
In 30 days, a work can be done by 20 men
In 1 day, a work can be done by (20 ×30)men =600men
For the first 6days, the man-days =(20×6)
120
So,after 6 days 8 men fell sick.
No. of workers at present =(20-8)men
=12 men
let, d be the no. of days man will complete the remaining work.
BTP
120+12d=600
or, 12d=600-120
or, 12d=480
or, d=480/12
or, d=40
The workers will take total 40+6= 46days