20 men finish a work 7 per hour a day by 10 days how many days 15 men finish a work done by 8 per hour a day
Answers
Answered by
0
Step-by-step explanation:
20 men working 7 hours a day can complete the work in 10 days 15 men working 1 hour a day can complete the work in (10 x 7) days (Less hours ⇒ More days)
1 man working 1 hour a day can complete the work in ( 10 x 7 x 20) days (Less men ⇒ More days)
1 man working 8 hours a day can complete the work in =
(10×7×20)
--------------
8×15
Days (More men ⇒ Less days)
(Less men ⇒ More days) = 35/3 days = 11⅔days.
I HOPE IT HELP YOU ✌️✌️✌️
THANKS YOU