20 men or 24 women can complete a piece of work in 20 days. If 30 men and 12 women under take to complete the work, the work will be complete in
Answers
20 men or 24 women can complete a piece of work in 20 days.
Number of days taken by 30 men and 12 women to complete the work.
⇒20 men = 24 women
⇒1 man = women
•°• 1 man = women
⇒30 men = × 30 women
•°• 30 men = 36 women
•°• 30 men + 12 women = 36 + 12
= 48 women
Now, M₁ = 24, M₂ = 48, W₁ = W₂ = 1, D₁ = 20 and D₂ = ?
M₁ × D₁ × W₂ = M₂ × D₂ × W₁
⇒ 24 × 20 × 1 = 48 × D₂ × 1
⇒ D₂ =
⇒ D₂ = 10 days
If a₁ men or b₁ women can finish a work in D days, then time taken by a₂ men and b₂ women to complete the work = days
Here, a₁ = 20, b₁ = 24, a₂ = 30, b₂ = 12 and D = 20
•°• Number of days = days
=
= days
= 10 days
Answer:
10 Days
Step-by-step explanation:
20 M = 20 Days, 24W=20 Days
30M+12W= x days
soln:
x= 20/ ( (30/20) +(12/24) )
= 20/ ( (3/2)+(1/2))
= 20 / ( 1.5+0.5 )
= 20/2
x= 10 days