20 men takes 52 days to build a wall. How many more men are required to build a wall, triple in size, in 60 days
Answers
Answered by
1
Answer:
20 52
x 60
Cross multipliying
x=20x60
52
x= 23.077 (approx)
Step-by-step explanation:
Answered by
6
Answer:
Your answer is 5
Step-by-step explanation:
Let x men are required to build the wall in 45 days.
Then x:15::60:45
⇒45x=15×60
⇒x=
45
15×60
x=20 men.
Hence, 20−15=5 more men are required.