20 men were employed to do some work in a certain time.But when 1/3rd of the scheduled time was over,it was found that only 1/4th work was completed.How many more men employed to completed the work in 3/4th of the originally scheduled time?
a.28
b.20
c.48
d.40
Answers
Answered by
10
Answer:
Step-by-step explanation:
Remaining Work =1-1/4=3/4
Remaining tym =3/4-1/3=5/12
(20*1/3)/(1/4) =(X*5/12)/3/4)
X=48
Extra=(48-20)=28 men
Answered by
1
Option 'a' is correct.
Step-by-step explanation:
Since we have given that
Part of time over =
Part of work completed =
Remaining part of work =
So, remaining work in remaining time is given by
According to question, it becomes,
Number of more men would be
Hence, Option 'a' is correct.
# learn more:
6. 40 men are employed to finish a work in 48 days. but it is found that in 24 days only 1/4 work is done. how many more men are required in order to finish the work in time? (a) 24 men (b) 16 men (c) 22 men (d) 20 men
https://brainly.in/question/5871321
Similar questions