Math, asked by AabhaSharma, 9 months ago

20 men were employed to do some work in a certain time.But when 1/3rd of the scheduled time was over,it was found that only 1/4th work was completed.How many more men employed to completed the work in 3/4th of the originally scheduled time?
a.28
b.20
c.48
d.40

Answers

Answered by radhe830222
10

Answer:

Step-by-step explanation:

Remaining Work =1-1/4=3/4

Remaining tym =3/4-1/3=5/12

(20*1/3)/(1/4) =(X*5/12)/3/4)

X=48

Extra=(48-20)=28 men

Answered by windyyork
1

Option 'a' is correct.

Step-by-step explanation:

Since we have given that

Part of time over = \dfrac{1}{3}

Part of work completed = \dfrac{1}{4}

Remaining part of work = 1-\dfrac{1}{4}=\dfrac{4-1}{4}=\dfrac{3}{4}

So, remaining work in remaining time is given by

\dfrac{3}{4}-\dfrac{1}{3}\\\\=\dfrac{9-4}{12}\\\\=\dfrac{5}{12}

According to question, it becomes,

\dfrac{20\times \dfrac{1}{3}}{\dfrac{1}{4}}=\dfrac{x\times \dfrac{5}{12}}{\dfrac{3}{4}}}\\\\20=x\times \dfrac{5}{12}\\\\12\times 4=x\\\\48=x

Number of more men would be

48-20=28\ men

Hence, Option 'a' is correct.

# learn more:

6. 40 men are employed to finish a work in 48 days. but it is found that in 24 days only 1/4 work is done. how many more men are required in order to finish the work in time? (a) 24 men (b) 16 men (c) 22 men (d) 20 men

https://brainly.in/question/5871321

Similar questions