20 men were working together to complete the work( gsw, joix. mcu ) in 20 days then the number of days were taken to complete the same work by 25 men's work plz help me i will mark you the brailiest
Answers
Answered by
1
Answer:
20 men=20 days
25 men=x days
x=20*20/25
x=400/25
x=16 days.
x is missing number.
Please mark me as brainliest If it helps you.