20 men working together complete a work in 20 days then number of days taken to complete the same work by 25 men walks
Answers
Answered by
1
Answer:
16 Days
Step-by-step explanation:
Using Work=men×days we get
Work=20×20
Work=400
Now, work is the same and the number of days is to be calculated
400=25×days
Days=16